Providence, Saint Joseph Hospital – Lab Chem Automation

PROJECT TYPE:

Acute Care Hospitals, Laboratories

LOCATION:

Burbank, CA

PROJECT VALUE:

1.085M

ARCHITECT:

ALA Architects

Lab Chem Automation Systems

The Stahl Team manages the multi-phased Lab Automation project, which began on March 25, 2021. Phase 1 included upgrading plumbing, electrical, and data for the DI Water System and installing a new Analyzer. Tasks included site demo prior to the installation of underground utilities to support the new DI water system and the modifications to existing infrastructure to support the relocation of refrigeration units. This work included saw-cutting of concrete and excavation for additional utilities, in addition to the seismic anchorage of equipment. The new Aitellicas Analyzers went live on 9/7/21. Sysmax analyzers were installed 3/28/22.

The team has completed phases 2 &3.  Phase 3 has been submitted to HCAi for review. We are expecting to be in construction in 2023.